Approval of Change Order #2 to Agreement F2018123 to Kelly Brothers, Inc. for Rock Seawall Installation relating to the Buckley's Pass Additional Harbor Access Project

Funds:

Special Assessment Revenues

Project is being constructed in the General Construction Fund $289,025.00 Account #301-3004-549-6515 Buckley’s Pass Project (PROJECT #BRDCUT)

No appropriation needed - within budget approved by Council based on Engineer’s Cost Estimate for Construction of $1,956,940.

Recommended Action:

City Council approval of Change Order #2 to Agreement F2018123 to Kelly Brothers, Inc., for Rock Seawall Installation.

Summary:

While driving sheet piles, the contractor discovered a rock layer along the entire length of the seawall alignment. As a result, the vinyl sheet panels must be installed by pre-forming a hole by punching, drilling or excavating the hard strata/rock. This rock seawall installation method was included as an optional item in the construction contract at $275 per linear foot. At 1,051 linear feet the additional cost is $289,025.

 

Construction Cost of Project:              $1,499,399.16

Change Order #2                                $   289,025.00

Total                                                    $1,788,424.16