Title: Harborwalk Pier at Justice Center
Funds:

Appropriation of up to $120,000 to expenditure account 118-3007-572-6599 Harborwalk HWPRJC

Appropriation of $120,000 of additional revenue projected of 1% sales tax to revenue account 118-0000-335-1801  1% Local Option Sales Tax

For purposes of: Design and Replacement of Existing Pier.

Recommended Action: City Council approval
Summary:

The pier behind the Justice Center has sunk significantly.  We recently had soil borings completed.  The engineer recommendations were to install new pilings to proper specifications. Due to the age and condition of the pier the railings and deck would also be replaced during this process.  

 

Estimated Project Costs:

Design   $20,000

Construction - $75,000 to $100,000

 

Department/Division: Public Works/Engineering
 